Global Uranium Details ANT Survey Metrics at the Astro Project

Passive seismic program at AS-1 target complete; results to guide planned winter ground EM program

Calgary, Alberta — Global Uranium Corp. (CSE: GURN | OTC: GURFF | FRA: Q3J) (the “Company“) is pleased to provide survey design and fieldwork metrics for the summer 2026 ambient noise tomography (“ANT”) program at the Astro Project (“Astro” or the “Project”) in the eastern Athabasca Basin, Saskatchewan. This update follows the Company’s October 8, 2026 announcement of fieldwork completion and provides further detail on the acquisition program supporting ongoing processing and interpretation. CAUR Technologies (“CAUR”) carried out the survey with field support from Axiom, under the direction of Project operator Cosa Resources Corp. (“Cosa”). Deployment began on June 17, 2026, and CAUR reported completion of the deployment campaign and crew demobilization by June 23, 2026.

The survey was designed around a planned deployment of 300 geophones, comprising 100 single-component and 200 three-component sensors. Eight field personnel worked in four two-person teams during deployment. CAUR reported deployment productivity of approximately 60 sensors per day in its campaign recap. The program included 21 days of seismic monitoring, which had been completed by July 12, 2026. It was confirmed on August 4, 2026 that sensor retrieval was complete. The survey focused on AS-1, a target area within the approximately 25-kilometre-long conductive corridor identified by the 2025 airborne Z-Axis Tipper Electromagnetic (“ZTEM”) survey. ANT uses recordings of ambient seismic noise to model subsurface shear-wave velocity. Variations in velocity can help interpret rock units, structures and possible alteration within the lower Athabasca sandstone and upper basement.

CAUR has prepared a preliminary report, with further processing and interpretation continuing. Global and Cosa intend to assess the ANT models alongside the ZTEM dataset to prioritize proposed ground electromagnetic (“EM”) surveying during the upcoming winter field season. Ground EM would provide more detailed definition of conductive targets ahead of potential drilling. The scope and timing of follow-up work remain subject to completed interpretation, funding, contractor availability and required approvals. Global expects to report interpretation results following technical review. Geophysical anomalies do not, on their own, establish the presence of uranium mineralization.

“This summer’s program went smoothly from deployment through retrieval, and we’re grateful to CAUR, Axiom and the Cosa team for running it so efficiently,” said Ungad Chadda, CEO of Global Uranium. “ANT gives us a new way to look beneath the surface at Astro without disturbing the ground. Combined with last year’s ZTEM results, it should help us decide where to focus our next round of fieldwork. We look forward to sharing the interpretation results once the technical review is complete.”

Figure 1. Astro Project boundary and approximate AS-1 target area, the focus of the 2026 ambient noise tomography (ANT) survey. The highlighted area is based on the survey plan and does not depict the final geophone deployment footprint or interpreted ANT results.

QUALIFIED PERSON

The scientific and technical information contained in this news release has been reviewed and approved by Jared Suchan, Ph.D., P.Geo., a Qualified Person as defined by NI 43-101″.

ABOUT GLOBAL URANIUM CORP.

Global Uranium Corp. focuses on exploring and developing uranium assets primarily in North America. The Company currently holds key uranium projects: the Wing Lake Project in the Mudjatik Domain of northern Saskatchewan, Canada; the Astro Project (with Cosa Resources Corp.) in the eastern Athabasca Basin, Saskatchewan; the Airline Project in the northern Wind River Basin, Wyoming, USA; as well as additional projects across the Gas Hills and Great Divide Districts in Wyoming.

ON BEHALF OF THE BOARD OF DIRECTORS

Ungad Chadda
CEO

587-330-0045
info@globaluranium.com

FORWARD-LOOKING STATEMENTS

Certain statements contained in this press release constitute forward-looking information. These statements relate to future events or future performance. The use of any of the words “could”, “intend”, “expect”, “believe”, “will”, “projected”, “estimated” and similar expressions and statements relating to matters that are not historical facts are intended to identify forward-looking information and are based on the Company’s current belief or assumptions as to the outcome and timing of such future events.

In particular, this press release contains forward-looking information relating to, among other things: the Project, including the prospectivity of the Project, its potential to host extensions of the McArthur River/Fox Lake Structural Corridor and other beneficial geological trends; and the Company’s and Cosa’s exploration plans with respect to the Project, including the Project’s candidacy for advanced geophysical exploration and drilling to delineate compelling targets. Various assumptions or factors are typically applied in drawing conclusions or making the forecasts or projections set out in forward-looking information, including the assumption that: the historical work done with respect to the Project is representative of the actual geological nature of the Project; that the Project may share the geological characteristics of nearby projects, deposits and mines; and that the Company and Cosa will successfully collaborate with respect to the exploration of the Project pursuant to the Option Agreement, including by progressing advanced geophysical exploration and drilling. Those assumptions and factors are based on information currently available to the Company. Although such statements are based on reasonable assumptions of the Company’s management, there can be no assurance that any conclusions or forecasts will prove to be accurate.

Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include: the risk that the Company does not earn-in to any interest in the Project pursuant to the Option Agreement; risks inherent in the Company and Cosa’s joint exploration of the Project, including the risk that the Company and Cosa disagree on the manner or timeline for the exploration of the Project and/or are unable to collaborate on the exploration of the Project successfully pursuant to the Option Agreement; risks inherent in the exploration and development of mineral deposits, including risks relating to receiving requisite permits and approvals, changes in project parameters or delays as plans continue to be redefined, that mineral exploration is inherently uncertain and that the results of mineral exploration may not be indicative of the actual geology or mineralization of a project; that mineral exploration may be unsuccessful or fail to achieve the results anticipated by the Company; that the characteristics of the Project may not reflect the characteristics of nearby projects, deposits and mines; operational risks; regulatory risks, including risks relating to the CSE’s approval of the share issuances pursuant to the Option Agreement and the acquisition of the necessary licenses and permits to conduct exploration on the Project; financing, capitalization and liquidity risks; title and environmental risks; and risks relating to the failure to receive all requisite regulatory approvals. The forward-looking information contained in this release is made as of the date hereof, and the Company is not obligated to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, except as required by applicable securities laws. Because of the risks, uncertainties and assumptions contained herein, investors should not place undue reliance on forward-looking information. The foregoing statements expressly qualify any forward-looking information contained herein.

The Canadian Securities Exchange has not reviewed, approved, or disapproved the contents of this ‎press release.‎

Explore Our Projects